ArcelorMittal yesterday announced the indefinite shut down of it’s Krakow, Poland blast furnace and steel making operations.
Due to weak demand and cheap Russian imports AM plans to cut back it’s European flat rolled production.
Tag Archives: Krakow
Huta Tadeusz Sendzimira
Images now at my website.
The ArcelorMittal plant in Nova Huta, a borough of Krakow, Poland was founded in 1949.
The mill was named Huta Lenin and the first iron from blast furnace No.1 was tapped in 1954.In 1955 an open hearth steel making shop was added and in 1956 a hot strip mill started production.
Blast furnaces No.2 and No.3 were completed in 1956 and 1958.
In between 1954-56 four coke oven batteries were built.
In 1961 a fourth blast furnace was added.
In 1966 the BOF melt shop containing two 100 ton vessels (a third vessel was added in 1971) was launched and the new large volume (2000m³) blast furnace No.5 was built.
In 1970 some of the old open hearth furnaces were replaced by two new Tandem furnaces.
In between 1978 and 1998 all BOFs were enlarged to 160 ton capacity.
In 1990 the mill got it’s new name Huta Tadeusz Sendzimira.
In June 1991 the open hearth steel plant was closed down.The Mittal steel group took over the site in 2005.Two years later a new state of the art wide hot strip mill was comissioned.